Ohio Code § 1514.05
Ohio Code § 1514.05. Reproduced from the official Ohio Revised Code, with a citation summary, verification link, and related provisions.
§ 1514.05.
(A) At any time within the period allowed an operator by section 1514.02 of the Revised Code to reclaim an area of land affected by surface or in-stream mining, the operator
may file a request, on a form provided by the chief of the division of mineral resources
management, for inspection of the area of land upon which the reclamation, other than
any required planting, is completed. The request shall include all of the following: (1) The location of the area and number of acres; (2) The permit number; (3) A map showing the location of the acres reclaimed, prepared and certified in accordance
with division (A)(11) or (12) of section 1514.02 of the Revised Code, as appropriate. In the case of an in-stream mining operation, the map also shall include, as applicable,
the information required under division (A)(18) of section 1514.02 of the Revised Code . The chief shall make an inspection and evaluation of the reclamation of the area of
land for which the request was submitted within ninety days after receipt of the request
or, if the operator fails to complete the reclamation or file the request as required,
as soon as the chief learns of the default. Thereupon, if the chief approves the reclamation, other than any required planting,
as meeting the requirements of this chapter, rules adopted thereunder, any orders
issued during the mining or reclamation, and the specifications of the plan for mining
and reclaiming, the chief shall issue an order to the operator and the operator's
surety releasing them from liability for one-half of the total amount of their surety
bond on deposit to ensure reclamation for the area upon which reclamation is completed. If the operator has deposited cash, an irrevocable letter of credit, or certificates
of deposit in lieu of a surety bond to ensure reclamation, the chief shall deliver
to the operator or the operator's authorized agent one-half of the amount so held. If the chief does not approve the reclamation, other than any required planting, the
chief shall notify the operator by certified mail. The notice shall be an order stating the reasons for unacceptability, ordering further
actions to be taken, and setting a time limit for compliance. If the operator does not comply with the order within the time limit specified,
the chief may order an extension of time for compliance after determining that the
operator's noncompliance is for good cause, resulting from developments partially
or wholly beyond the operator's control. If the operator complies within the time limit or the extension of time granted
for compliance, the chief shall order release of the performance bond in the same
manner as in the case of approval of reclamation, other than any required planting,
by the chief, and the chief shall proceed as in that case. If the operator does not comply within the time limit and the chief does not order
an extension, or if the chief orders an extension of time and the operator does not
comply within the extension of time granted for compliance, the chief shall issue
another order declaring that the operator has failed to reclaim and, if the operator's
permit has not already expired or been revoked, revoking the operator's permit. The chief shall thereupon proceed under division (C) of this section. (B) At any time within the period allowed an operator by section 1514.02 of the Revised Code to reclaim an area affected by surface mining, the operator may file a request, on
a form provided by the chief, for inspection of the area of land on which all reclamation,
including the successful establishment of any required planting, is completed. The request shall include all of the following: (1) The location of the area and number of acres; (2) The permit number; (3) The type and date of any required planting of vegetative cover and the degree of
success of growth; (4) A map showing the location of the acres reclaimed, prepared and certified in accordance
with division (A)(11) or (12) of section 1514.02 of the Revised Code, as appropriate. In the case of an in-stream mining operation, the map also shall include the information
required under division (A)(18) of section 1514.02 of the Revised Code . The chief shall make an inspection and evaluation of the reclamation of the area of
land for which the request was submitted within ninety days after receipt of the request
or, if the operator fails to complete the reclamation or file the request as required,
as soon as the chief learns of the default. Thereupon, if the chief finds that the reclamation meets the requirements of this
chapter, rules adopted under it, any orders issued during the mining and reclamation,
and the specifications of the plan for mining and reclaiming and decides to release
any remaining performance bond on deposit to ensure reclamation of the area on which
reclamation is completed, within ten days of completing the inspection and evaluation,
the chief shall order release of the remaining performance bond in the same manner
as in the case of approval of reclamation other than required planting, and the chief
shall proceed as in that case. If the chief does not approve the reclamation performed by the operator, the chief
shall notify the operator by certified mail within ninety days of the filing of the
application for inspection or of the date when the chief learns of the default. The notice shall be an order stating the reasons for unacceptability, ordering further
actions to be taken, and setting a time limit for compliance. If the operator does not comply with the order within the time limit specified,
the chief may order an extension of time for compliance after determining that the
operator's noncompliance is for good cause, resulting from developments partially
or wholly beyond the operator's control. If the operator complies within the time limit or the extension of time granted
for compliance, the chief shall order release of the remaining performance bond in
the same manner as in the case of approval of reclamation by the chief, and the chief
shall proceed as in that case. If the operator does not comply within the time limit and the chief does not order
an extension, or if the chief orders an extension of time and the operator does not
comply within the extension of time granted for compliance, the chief shall issue
another order declaring that the operator has failed to reclaim and, if the operator's
permit has not already expired or been revoked, revoking the operator's permit. The chief then shall proceed under division (C) of this section. (C) Upon issuing an order under division (A) or (B) of this section declaring that the
operator has failed to reclaim, the chief shall make a finding as to the number and
location of the acres of land that the operator has failed to reclaim in the manner
required by this chapter. The chief shall order the release of the performance bond in the amount of five
hundred dollars per acre for those acres that the chief finds to have been reclaimed
in the manner required by this chapter. The release shall be ordered in the same manner as in the case of other approval
of reclamation by the chief, and the chief shall proceed as in that case. If the operator has on deposit cash, an irrevocable letter of credit, or certificates
of deposit to ensure reclamation of the area of the land affected, the chief at the
same time shall issue an order declaring that the remaining cash, irrevocable letter
of credit, or certificates of deposit are the property of the state and are available
for use by the chief in performing reclamation of the area and shall proceed in accordance
with section 1514.06 of the Revised Code . If the operator has on deposit a surety bond to ensure reclamation of the area of
land affected, the chief shall notify the surety in writing of the operator's default
and shall request the surety to perform the surety's obligation and that of the operator. The surety, within ten days after receipt of the notice, shall notify the chief
as to whether it intends to perform those obligations. If the surety chooses to perform, it shall arrange for work to begin within thirty
days of the day on which it notifies the chief of its decision. If the surety completes the work as required by this chapter, the chief shall issue
an order to the surety releasing the surety from liability under the bond in the same
manner as if the surety were an operator proceeding under this section. If, after the surety begins the work, the chief determines that the surety is not
carrying the work forward with reasonable progress, or that it is improperly performing
the work, or that it has abandoned the work or otherwise failed to perform its obligation
and that of the operator, the chief shall issue an order terminating the right of
the surety to perform the work and demanding payment of the amount due as required
by this chapter. If the surety chooses not to perform and so notifies the chief, does not respond to
the chief's notice within ten days of receipt thereof, or fails to begin work within
thirty days of the day it timely notifies the chief of its decision to perform its
obligation and that of the operator, the chief shall issue an order terminating the
right of the surety to perform the work and demanding payment of the amount due, as
required by this chapter. Upon receipt of an order of the chief demanding payment of the amount due, the surety
immediately shall deposit with the chief cash in the full amount due under the order
for deposit with the chief. If the surety fails to make an immediate deposit, the chief shall certify it to
the attorney general for collection. When the chief has issued an order terminating the right of the surety and has the
cash on deposit, the cash is the property of the state and is available for use by
the chief, who shall proceed in accordance with section 1514.06 of the Revised Code .
Source: official Ohio text · Last verified 2026-08-27
At a glance
- Citation: Ohio Revised Code § 1514.05
- Jurisdiction: Ohio
- Code: Ohio Revised Code
- Text: transcribed from the official source (verify below)
Verify the text
Statute text is transcribed from the official Ohio Revised Code. Confirm it against the primary source before relying on it:
Not legal advice. Verify against the official source and consult a licensed Ohio attorney.
Common questions
What is the source of Ohio Revised Code § 1514.05?
The text above is transcribed from the Ohio Revised Code, the codified statutes of Ohio. The official publisher link appears under "Verify the text" on this page.
What subject does Ohio Revised Code § 1514.05 address?
It addresses the rule set out in the section text. Read the section together with the surrounding provisions listed under "Nearby provisions" for the full picture.
Is Ohio Revised Code § 1514.05 still in force?
Statutes are amended, repealed, and renumbered every session. Confirm the current version at the official Ohio source before relying on this text.
Can this page be used as legal advice?
No. This is a reference transcription for research. Applying Ohio law to your facts requires a licensed Ohio attorney who can review the specifics.