Ohio Code § 5525.17
Ohio Code § 5525.17. Reproduced from the official Ohio Revised Code, with a citation summary, verification link, and related provisions.
§ 5525.17.
(A)(1) If a contractor has not commenced work within a reasonable time, or does not carry
the same forward with reasonable progress, or is improperly performing the work, or
has abandoned, or fails or refuses to complete a contract entered into under Chapters
5501., 5503., 5511., 5513., 5515., 5516., 5517., 5519., 5521., 5523., 5525., 5527.,
5528., 5529., 5531., 5533., and 5535. of the Revised Code, the director of transportation
shall make a finding to that effect and so notify the contractor in writing, and the
rights of the contractor to control and supervise the work shall immediately cease. The director shall forthwith give written notice to the sureties on the bonds of
such contractor of such action. (2) If, within ten days after the receipt of such notice, such sureties on the contract
performance bond or any one or more of them notify the director in writing of their
intention to enter upon and complete the work covered by such contract, such sureties
shall be permitted to do so and the director shall allow them thirty days, after the
receipt of such notice in writing, within which to enter upon the work and resume
construction, unless such time is extended by the director for good cause shown. If such sureties do not carry the same forward with reasonable progress, or if they
improperly perform, abandon, or fail to complete the work covered by any such contract,
the director shall complete the same in the manner provided in this section. (3) Except as provided in division (A)(4) of this section, in the event the sureties
on the contract performance bond, or any one or more of them, notify the director
in writing of their intention to enter upon and complete the work covered by such
contract, and then fail or refuse to so complete, any additional costs reasonably
incurred by the director as a result of such failure or refusal shall be computed
by the director and become the liability of such surety, which is not limited by the
amount of the contract performance bond. (4)(a) In the event the sureties on a contract performance bond that relates to a major
bridge project, or any one or more of them, notify the director in writing of their
intention to enter upon and complete the work covered by such contract, and then fail
or refuse to so complete, any additional costs reasonably incurred by the director
as a result of such failure or refusal shall be computed by the director and become
the liability of such surety in an amount not to exceed one hundred fifteen per cent
of the contract performance bond. (b) As used in division (A)(4)(a) of this section, “ major bridge project ” means a bridge project that spans the Ohio river for a contract that was awarded
with the allowances authorized under division (D) of section 5517.011 of the Revised Code . (5) If the surety fails to pay the amount computed by the director under division (A)(3)
or (4) of this section, the director shall certify the facts to the attorney general,
who shall proceed to collect such additional costs from the surety and the amount
so collected shall be paid into the state treasury to the credit of the fund from
which the excess cost was originally paid. (B) If, after receiving notice of the action of the director in terminating the control
of the contractor over the work covered by the contract, the sureties on such contract
performance bond do not within ten days give the director the written notice provided
for in this section, the director shall cause that portion of the work which remains
uncompleted to be re-estimated and relet in accordance with the requirements applicable
to original bids; or in the event the director determines with the approval of the
controlling board that an extraordinary emergency exists, the director may contract
for the completion of the work without advertising for bids, if the director considers
it to be in the best public interest. (C) Before entering into a contract for the completion of any such improvement in accordance
with division (B) of this section, the director shall require a contract performance
bond and a payment bond with sufficient sureties each in an amount equal to one hundred
per cent of the estimated cost of completing the work, and conditions relating to
the bonds of original contractors shall apply to such bonds. (D)(1) If the cost of completing such work under division (C) of this section exceeds the
amount set aside or apportioned therefor, the remainder of the cost shall be paid
from the appropriations from the state highway operating fund available for the use
of the department of transportation and against which no contractual obligations exist. (2) Subject to the limitation specified in division (A)(4) of this section, if the cost
of completing any such improvement exceeds the portion of the contract price remaining
unpaid to the original contractor at the time of default, such excess shall be computed
by the director and becomes the liability of such contractor or surety or both. If either the contractor or surety fails to pay such amount, the director shall
certify the facts to the attorney general, who shall proceed to collect such excess
cost from the contractor and the sureties upon the contract performance bond, and
the amount so collected shall be paid into the state treasury to the credit of the
fund from which the excess cost was originally paid. (E) Where the estimated cost of completing a defaulted contract does not exceed five
thousand dollars, the director may complete the same by force account, or by a contract
let without advertisement.
Source: official Ohio text · Last verified 2026-08-27
At a glance
- Citation: Ohio Revised Code § 5525.17
- Jurisdiction: Ohio
- Code: Ohio Revised Code
- Text: transcribed from the official source (verify below)
Verify the text
Statute text is transcribed from the official Ohio Revised Code. Confirm it against the primary source before relying on it:
Not legal advice. Verify against the official source and consult a licensed Ohio attorney.
Common questions
What is the source of Ohio Revised Code § 5525.17?
The text above is transcribed from the Ohio Revised Code, the codified statutes of Ohio. The official publisher link appears under "Verify the text" on this page.
What subject does Ohio Revised Code § 5525.17 address?
It addresses the rule set out in the section text. Read the section together with the surrounding provisions listed under "Nearby provisions" for the full picture.
Is Ohio Revised Code § 5525.17 still in force?
Statutes are amended, repealed, and renumbered every session. Confirm the current version at the official Ohio source before relying on this text.
Can this page be used as legal advice?
No. This is a reference transcription for research. Applying Ohio law to your facts requires a licensed Ohio attorney who can review the specifics.